United Kingdom Atomic Energy Authority: A report on
the service provided by the Authority
Summary of report (html format)
Full text (pdf format)
Adobe Acrobat Reader can be downloaded from http://www.adobe.com
Summary
On 30 July 1991 the Secretary of State for Trade and Industry referred
to the Commission certain questions relating to the efficiency and costs
of and the service provided by the United Kingdom Atomic Energy Authority
(AEA) in carrying out its statutory functions and in meeting the objectives
set by the Secretary of State for Energy (see Appendix 1.1).
In this chapter we discuss the main issues arising from the reference
which required a wide-ranging inquiry covering both AEA's corporate affairs
and the diverse activities of its nine businesses. A summary of our recommendations,
including, wherever possible, specific target dates for implementation
agreed with AEA, appears at the end of the report in Chapter 17. We draw
attention to key recommendations in paragraph 46.
Background
When AEA was formally created by the Atomic Energy Authority Act 1954,
its central role was to lead the development of nuclear technology in
the United Kingdom. In 1965 it was allowed to extend its activities into
non-nuclear research and development (R&D) under contract for customers
but nuclear work still predominated. At its peak in the early 1960s it
had over 40,000 staff. Substantial nuclear activities were transferred
in the 1970s to other organisations including British Nuclear Fuels plc
(BNFL) and the Ministry of Defence (MOD) and AEA's staff was reduced by
around two-thirds. Significantly, however, it was left with a number of
widely scattered nuclear sites, subject to varying degrees of contamination
which would have to be dealt with eventually, from Winfrith on the south
coast of England to Dounreay on the north coast of Scotland.
There was another important change in 1986 when AEA's finances were
placed on a trading fund basis. Essentially, this meant that it was no
longer vote-funded but required to secure its income through commercial
agreements with customers. The effect of this change has been enhanced
in particular by Government decisions to cut back the funding for AEA's
major nuclear programmes and to impose a moratorium on future nuclear
stations until at least post-1994, further reducing work for AEA.
AEA responded by carrying out a major review of its strategy, which
led to a fundamental change in April 1990 from a management structure
based on sites to a new business-led structure which managed businesses
across sites. The role of sites was adjusted to cover primarily support
services meeting the needs of the businesses. AEA's aim eventually is
to transform AEA into `a fully commercial, successful and profitable technology-based
services and products operation', taking advantage of what it sees as
significant synergy between its nuclear and non-nuclear businesses.
Meanwhile, the Government has made it clear that it supports AEA in
carrying forward this major restructuring `which is aimed at increasing
competitiveness, cutting costs, providing better value for money for its
customers and increasing profitability'. It looks to AEA `to achieve returns
to enable it to fund the costs of restructuring and make a return for
the Exchequer'. It has told AEA that its objectives will be reviewed not
later than the summer of 1993 (see Appendix 1.3). In this report, we refer
to the various funding and other arrangements AEA has made to implement
this restructuring as the `restructuring programme'.
Performance
In the terms of reference, we first are asked whether, in carrying out
its functions and meeting the objectives set by the Secretary of State,
AEA could improve its efficiency and thereby reduce its costs without
affecting the quality of the goods and services it provides.
In reviewing AEA's performance, we have had to keep in mind that it
is an organisation undergoing fundamental change. This has created problems
for both AEA and ourselves. AEA has had to respond to our wide-ranging
requirements for information at a time when it was already under considerable
pressure, and we are grateful for its ready response. For our part, we
have been looking at a new structure which is still evolving. AEA's nine
businesses with forecast external sales ranging from £14 million
to £126 million in 1991/92 had been in operation for only 16 months
when we started the inquiry. It is too soon to reach a firm conclusion
on this development (see paragraph 1.10). Similarly, although we welcome
them, we have been unable fully to evaluate proposed changes such as the
crucially important new financial information system (FIS) and the new
sites structure, both to be implemented in April 1992.
We have also taken two general considerations into account. First, although
AEA's nuclear activities are in decline, they still account for some two-thirds
of the external sales of AEA's businesses, and are relatively secure,
since the Government is their major customer. We note that the nuclear
businesses, and, in fact, AEA's other activities as well, have so far
been virtually unaffected by the recession. This degree of security is
a significant advantage, although it is to some extent counterbalanced
by other factors; there is a declining programme of Government-funded
nuclear research, and AEA's major customer sets its financial and other
objectives.
Secondly, AEA's diverse businesses (four nuclear and five industrial),
with activities ranging from nuclear research to petroleum services, rest
uneasily in the public sector where their entrepreneurial activities are
inevitably somewhat constrained. AEA clearly cannot expect freedom to
take on expensive new ventures in circumstances where the taxpayer will
be left with the bill if things go wrong. Equally, however, we see little
prospect of AEA meeting its ambitious financial objective of funding the
cost of its restructuring programme and making a return for the Exchequer,
while its business expansion is constrained. It seems to us that this
dilemma is only likely to be satisfactorily resolved by removing AEA's
business activities from the public sector so far as this is practicable.
We recognise that this would entail both some financial reconstruction
and satisfactory arrangements for taking care of AEA's legacy of nuclear
sites. It would be most apt to determine the appropriate course of action
after completion of the review of nuclear power which the Government has
announced it intends to carry out in 1994 (see paragraph 1.42); the new
business structure will by then have had the opportunity to prove its
worth.
We also note that AEA's businesses have the expense and inconvenience
of being spread over widely dispersed sites which are too extensive for
their needs and in most cases difficult fully to exploit commercially
because of problems of location and nuclear contamination. It is not surprising
that relatively remote sites chosen for their suitability for nuclear
development are less convenient for other business purposes. Dounreay,
Windscale and Winfrith all fall into this category. As we have indicated,
this spread of sites is a legacy of AEA's nuclear activities. AEA intends
to continue to rationalise sites, particularly those which are reasonably
adjacent, enabling staff relocation costs to be contained and avoiding
the potential problem of staff refusing to move with the business. The
Risley/Culcheth sites are in this category. The Harwell/Culham sites are
another possibility in due course. Meanwhile we welcome the steps AEA
has taken and is continuing to take to reduce its very high overheads,
although we fear that under present arrangements they are likely to remain
uncomfortably large (see paragraph 1.34).
Taking these considerations into account, we believe that AEA in carrying
out its functions could continue to improve its efficiency and reduce
its costs without affecting the quality of goods and services it provides.
AEA plans to reduce its staff further, by about a sixth, in order to reduce
costs and achieve a closer match of manpower with the needs of the businesses.
We have noted particular weaknesses in financial and project control,
investment appraisal and marketing, and have made recommendations which
should result in further improvements in efficiency in these areas. We
are also asked whether the quality of AEA's goods and services could be
improved without any increase in costs; it follows from the above that
it could.
The final broad question in the terms of reference is the extent to
which alteration of quality might generate higher net revenue. Our survey
of AEA's customers indicated that its technical performance was well thought
of. Customers were least satisfied with its achievement of milestones
and deadlines, contract administration, and marketing and provision of
pre-contract information. It is reasonable to suppose that improvements
in these areas would in due course generate higher net revenue, and we
have made a number of recommendations to assist this process.
We now turn to the particular questions in the terms of reference.
(a) The efficient and economic use of manpower
In the course of its restructuring programme, AEA has reduced its staff
from some 13,600 in 1988 to around 9,600 by 31 March 1991 and it expects
a further reduction of about 1,500 by 31 March 1995. Staff costs are an
important element in site overheads and AEA has recognised that further
reductions are an essential part of the change to a corporate sites structure
in April 1992.
We have concluded that the proportion of personnel and training staff
in the workforce is unusually high and have recommended that within the
six months following the introduction of the new corporate personnel service,
in April 1992, the numbers should be reviewed.
We have also concluded that quantifiable objectives for non-industrial
staff are not always being set; the productivity bonuses for industrial
employees, which are based solely on attendance measures, are not related
to increased productivity; and there is a need for further manpower reductions
to bring numbers into line with expected reductions in work. We have recommended
the setting of quantifiable and challenging objectives for all non-industrial
staff; review of the operation of all bonus and productivity schemes for
industrial employees; and that AEA should continue to adjust workforce
numbers in order to reduce costs and achieve a close match of manpower
with the needs of the business.
To reinforce and support this endeavour, we believe that AEA's consultation
and bargaining machinery and pay structure should move away from the Civil
Service model to arrangements more suited to the new business-led organisation.
We have made a number of recommendations to this end.
(b) The economy, efficiency and effectiveness of the implementation
of the restructuring programme
The restructuring programme is an essential part of AEA's strategy.
At present AEA estimates that in round figures it will cost £392
million of which £279 million will be borne by AEA and £113
million by Government grant. Additional restructuring costs may arise
from the proposed closure of the Dounreay Prototype Fast Reactor (PFR),
the commitment to take back staff seconded to the Joint European Torus
(JET) fusion research project and increased contracting out.
Over 60 per cent of the programme are accounted for by people-related
costs, and the handling of this tranche of expenditure is therefore crucial
to our assessment of the implementation of the programme. In AEA's view,
the significant reduction in staff necessary to place its nine businesses
on a viable footing has been facilitated by the introduction of special
early release terms (SERT). We have found that in over 2,500 cases of
early release under SERT there have been isolated instances where released
employees have been re-engaged for specific tasks on a short-contract
basis. But these few cases do not detract from the general efficiency
and effectiveness of the implementation of a massive redundancy programme,
which has speedily and flexibly reduced staff numbers without industrial
unrest and any severe effects on staff morale. We have, however, been
unable to reach a firm conclusion on the economy of the implementation
of the redundancy programme because AEA has not produced overall costings
either of the redundancy options open to it or of extending the restructuring
process, as envisaged originally, over a longer period. We acknowledge
the difficulties of producing overall costings in an evolving situation
but in our view useful broad-brush comparisons of options could and should
have been produced at the significant stages of the programme, for example
at the commencement and when each major closure decision was reached.
On the face of it, the redundancy programme could have been implemented
at lower cost by a less liberal application of SERT terms. Against this
AEA says that the unquantifiable effects of possible industrial unrest
and loss of staff morale should be taken into account.
As to the restructuring programme as a whole, we are concerned that,
although the costs associated with each segment of the programme have
been reviewed against broad business objectives, there is little evidence
of costed options having been prepared prior to decisions on restructuring
spend. Moreover, although corporate management has been involved by way
of general guidance and some initiatives, much of the responsibility for
the development of restructuring plans has been placed on site and business
management, with the focus on sites and businesses to the possible neglect
of the overall corporate position. The introduction of the Chief Executive's
restructuring committee in September 1991 was a useful step, taken somewhat
late in the day, given the magnitude of the expenditure.
We appreciate the problems, inherent in any appraisal, of developing
accurate estimates but have concluded that tighter control of restructuring
expenditure should be introduced for the remaining £80 million of
the programme which has not yet been committed. We have accordingly recommended
that AEA should prepare before June 1992 a reasonably broad-brush costing
of the options open to it for the remainder of the existing programme
in order to establish that future spend is directed in the most profitable
way.
We calculate that AEA's estimate that it would be free of restructuring
debt by 2002 is dependent upon earning net profits of around £28
million a year over the period 1994/95 to 2001/02, or three times its
1991/92 forecast net profits. The attainment of this level of net profits
is critically dependent on AEA's ability to achieve increased productivity
to offset the growth in costs and to make up its loss of traditional nuclear
business by increases in decommissioning and radioactive waste management
operations (DRAWMOPS) work and particularly by expanded United Kingdom
private sector and overseas sales. This seems to be unduly optimistic.
We also believe that, as argued by AEA, the debt burden stemming from
the cost of restructuring is inhibiting the realisation of its full commercial
potential. Moreover, the rising interest burden, the accumulated deficit
and heavy borrowing have resulted in an unsound financial position, and
an annual requirement for a letter of comfort from the Department of Energy
(DEn) guaranteeing financial support to justify AEA's continuing to trade.
We have recommended that after the Government's review of the future of
nuclear power in the United Kingdom in 1994, it should look at the possibility
of a financial reconstruction with existing restructuring-related borrowing
being wholly or partly written off. Meanwhile any additional restructuring
driven by Government decision regarding AEA's nuclear activities should
be grant-funded in order to avoid any further distortion of AEA's financial
structure.
(c) The efficient and economic use of physical assets
We have already indicated that AEA has too many sites (see paragraph
1.11) but that its options for rationalisation are constrained. We have
nevertheless found that there is scope for improved management of AEA's
property assets. The variation in information on performance between sites
reflects, in part, differences in activities and types of accommodation
but it would be beneficial if such information was subject to systematic
analysis and review. We have therefore recommended that the responsibilities
of the proposed corporate Director of Estates should include the encouragement
of `best practice' across sites and the comparison of costs between sites
and with local market prices.
We have looked in some detail at the decision to relocate Corporate
Headquarters (CHQ) at Harwell, and have concluded that whilst there may
have been good reasons for the decision, it would nevertheless have been
wiser to have carried out detailed cost benefit analysis of all available
options, given the large sums involved. We have recommended that AEA's
own investment guidelines should be strictly followed in relation to estates
projects.
We have also recommended that AEA should revalue its land and buildings
at least once every five years. We understand that it is AEA's intention
to revalue all its properties in 1992. In our view, consideration should
be given to revaluing them on a rolling basis thereafter. Finally, as
regards properties, we have recommended that AEA's internal tenants should
be charged market rents.
As to other physical assets, we have noted that AEA has longstanding
procedures which should encourage their economic and efficient use. We
have, however, recommended that AEA should develop reports that enable
each business and site to show on a regular basis whether their major
assets are earning an appropriate return.
(d) The control of working capital
We have concluded that more effective monitoring of working capital
is necessary and have recommended that the present budgeting system should
be extended to incorporate an integrated phased balance sheet and funds
flow statement. We have also recommended that a set of target criteria
for working capital items should be established, together with targets
for invoice production and despatch. We noted in particular that invoicing
delays have occurred and that there have been other weaknesses in contract
administration. AEA indicated that closer attention would be paid to these
matters and agreed that the Requirements and Guidelines document, which
it planned to issue by April 1992, should make the project manager clearly
responsible for invoicing and ensuring that payment is received.
(e) The methods for determining the nature, amount and timing of
capital and `recovered' expenditure and the allocation of expenditure
between these categories
In its expenditure on fixed and durable assets, AEA draws a distinction
between those projects that are directed toward meeting the needs of a
particular customer, which AEA treats as `revenue schemes' funded by `recovered
expenditure'; and projects that have a wider customer application, which
it regards as capital expenditure. In some cases, the distinction may
be somewhat arbitrary. Both types of scheme are subject in principle to
the same assessment and approval procedures and we have concluded that
the allocation of expenditure between them is a matter primarily for negotiation
between AEA and its customers, most particularly DEn.
(f) The control of capital and recovered expenditure
We have concluded that AEA gives insufficient attention to the range
of feasible options associated with meeting a particular project objective;
the variation in the way projects are presented indicates a lack of effective
control; investment guidelines applying to revenue schemes and infrastructure
projects are inappropriate and unsatisfactory; insufficient use is made
of sensitivity analysis; and the Financial Manual should be revised in
order to strengthen the basis of appraisals. We have made a number of
recommendations aimed at improving investment procedures, particularly
in the areas of appraisal and control.
(g) The methods for allocating costs among management units
It was not until four years after the change to trading fund status
that AEA began to move towards standardisation of procedures for collection,
classification and allocation of site service department costs, although
it had been recognised that such standardisation would facilitate monitoring
and control of costs. We have concluded that standardisation of the accounting
procedures for site services departments might have been effected much
earlier and recommended that the required changes should be implemented
by April 1993.
(h) The methods for determining the level of charges to customers,
including the appropriate level of overheads
Bearing in mind AEA's possibly unique spread of skills and its monopoly
position in a substantial area of its activities, we have considered whether
there was any danger of AEA exploiting its customers by overcharging.
Its policy of seeking full commercial viability by raising its level of
profit is, however, explicitly supported by DEn in its role as AEA's de
facto owner, despite also being AEA's largest customer. AEA's other major
customers are mostly both technically informed and also able to exercise
a degree of buyer power. Limited data are presently available on the profitability
of AEA's individual businesses, particularly at product level, but its
overall profitability, around 9 per cent on historic cost capital employed
in 1990/91, is not excessive. We have concluded that AEA's policy of charging
on the basis of full cost recovery, including a reasonable return on capital
employed, is appropriate and consistent with its objective of seeking
full commercial viability.
We have also concluded that AEA's shift away from cost-plus pricing is
to be welcomed and that fixed-price contracts, wherever they are practicable,
are a more satisfactory system of charging than per diem pricing. We have
made a number of recommendations aimed at safeguarding customer interests
and sharpening the incentives for AEA to continue to enhance its cost
efficiency. We have also recommended that AEA should introduce a new system
of arm's length inter-business charging aimed at improving accountability
and economic efficiency. We recognise that this may require some additional
ground rules or `rules of thumb' about acceptable profit margins in order
to avoid undue complexity and inter-business disputes.
As regards overhead charges, we have noted that overheads are a key
element in AEA's costs; they can account, for example, for around two-thirds
of per diem costs. Their main component is the cost of accommodation and
associated services, including security costs. We have noted AEA's continuing
efforts to reduce its overheads; our recommendations will assist it in
this endeavour.
AEA's overheads include the cost of its discretionary research programmes.
We have concluded that the level of AEA's charges for such work is appropriate.
(i) The appropriateness of financial and other information systems
for the adequate control of costs and revenue and for the pursuit of commercial
objectives
Before the corporate Information Technology (IT) Directorate was established
late in 1989, AEA had no corporate IT strategy. We have concluded that
its slow adoption of such a strategy has resulted in uncoordinated and
incompatible site-based management information systems (MIS) and computer
hardware. These systems do not provide the information necessary to support
decisions, particularly at business level. AEA is now taking steps to
develop a strategy appropriate to the new business structure. Good progress
is being made and a new FIS will come into use in April 1992. However,
a considerable backlog of work remains to be dealt with before AEA will
have MIS which fully meet its corporate needs and the needs of its individual
businesses. We have made a number of recommendations to assist in its
progress towards this goal.
(j) The efficient implementation of the safety procedures and
standards agreed with or imposed by the safety authorities
AEA's safety management system is currently based on a three-tier approach,
corporate, sites and businesses. However, sites' responsibilities for
safety will be removed from April 1992. Safety management costs are a
forecast £36 million, or 8 per cent of turnover, in 1991/92. AEA
told us that the percentage of staff time devoted primarily to safety-related
matters was similar to that found in other major United Kingdom nuclear
undertakings. Although international comparisons were difficult because
of different regulatory systems and requirements, where similar organisations
existed safety costs had also been found to be similar. As to safety performance,
we were told by the regulators that AEA's performance was good. We have
recommended that in making regular reviews of the cost and effectiveness
of its safety arrangements AEA should compare them with safety performance
in the United Kingdom and elsewhere.
(k) The economy, efficiency and effectiveness of the implementation
of the recommendations made by the Advisory Council on Science and Technology
(ACOST) in respect of AEA's research programme
Since the second ACOST report in November 1990, AEA has introduced a
number of changes in the procedures for selecting, approving, controlling
and monitoring R&D projects related to new products and business opportunities.
These changes have taken account of each of the ACOST recommendations
except that relating to provision of a fund for projects initiated by
the Chief Scientist, which is dependent on AEA's commercial success. We
have concluded that AEA has effectively implemented the ACOST recommendations.
Certain other matters arising from our inquiry are, in our view, particularly
important.
Structure and organisation
AEA's existing sites structure will be abolished in April 1992 and replaced
by corporately-provided services demanded and paid for by the businesses.
We have welcomed this development which we believe is more appropriate
to the needs of the new business-led organisation.
To deal with DRAWMOPS, AEA has established a Corporate DRAWMOPS Directorate
(CDD). CDD's duties include management of the work required to meet AEA's
waste management and decommissioning liabilities. We have concluded that
every effort should be made to ensure that this work is open to competitive
tender from non-AEA businesses, and have welcomed the steps now being
taken by CDD in that direction.
AEA's annual report and accounts record contingent liabilities in respect
of costs to be incurred in the treatment and disposal of nuclear wastes
and in decommissioning plant related to work undertaken for Government
and public sector organisations, generally prior to 1 April 1986. Although
these organisations have agreed in principle to meet these liabilities,
currently estimated at £3 billion to £4 billion, the association
of most of them with AEA sites limits its freedom to develop such sites
in the most commercially effective way. Moreover, these liabilities impede
AEA's progress to independent commercial viability. As foreshadowed in
paragraph 1.10, we have recommended that in three years or so, after the
Government's review of nuclear power in the United Kingdom, AEA should
initiate a further strategic review to assess the position and future
development. At that stage, depending on the prevailing circumstances,
consideration should be given to a range of possibilities including separation
of AEA into two businesses, nuclear and non-nuclear; separation of some
of the existing businesses; creating a separate organisation to take over
the nuclear-related plant, buildings and locations no longer required
for AEA's continuing activities together with the associated decommissioning
and radioactive waste treatment and disposal programme; and continuing
as at present for a further period.
Planning
AEA's planning at both corporate and business levels needs to be sharpened
up. We have made a number of recommendations concerning particularly the
setting of specific, quantified, medium-term goals covering efficiency
and quality of service; and a strategic review of options available to
each business. We have also recommended that DEn's approach to setting
AEA's return on capital employed (ROCE) target should have more explicit
regard to the profit levels necessary to make AEA self-funding.
The range of products of AEA's industrial businesses is very wide, and
the scale of operations sometimes correspondingly small. We are concerned
that not all these activities may be commercially viable, particularly
as AEA has been unable routinely to provide estimates of the profitability
of product groups or products. AEA itself is aware of this potential difficulty
and has made some progress in reducing its industrial product range. The
new FIS (see paragraph 1.36) should reinforce the necessary continuing
process of developing a portfolio of commercially successful products.
We, for our part, have recommended improvements in AEA's planning at product-group
level which address the need for AEA to determine which of its activities
are not making a sufficient return and then to take appropriate action.
Marketing
AEA is already taking steps to remedy weaknesses in its approach to
identifying relevant markets and its knowledge of new markets. We have
made a number of recommendations aimed at supporting these steps. We have
also recommended that AEA should apply `best practice' marketing structures
more uniformly across its businesses; increase the level of training,
for example by secondment to suitable organisations; recruit more trained
and experienced marketing staff; review its overall marketing spend and
marketing strategies; and introduce procedures for evaluating the cost-effectiveness
of its marketing.
Key recommendations
We have made 58 recommendations, all of which we would expect to assist
AEA in improving its performance. We have, however, identified a dozen
of these as key recommendations by setting them out in bold type in Chapter
17.
Conclusion
It is inevitable that this report concentrates on areas where AEA's
performance could be improved. AEA itself recognises that it still has
a long way to go to complete its transformation into a fully commercial
operation (see paragraph 1.5). In our overall assessment of the public
interest, however, we need to give proper weight to AEA's achievements
since it embarked on its new business-led strategy in 1988. It has moved
from a location-based management structure providing a service on behalf
of the Government to a much more commercially driven business-based organisation.
As part of this process, it has made substantial progress in changing
the culture of the organisation by promoting the commercial awareness
and customer orientation of its staff. Simultaneously, as we have already
indicated, it has successfully managed a radical reduction in staff numbers
and substantially reduced its infrastructure costs. It has also commenced
a fundamental reform of its MIS.
We are required to consider whether, in relation to any matter falling
within our terms of reference, AEA is pursuing a course of conduct which
operates against the public interest. We find that it is not doing so.
It is clear from the range of our recommendations that we have found deficiencies
in AEA's performance in a number of areas. However, we believe that it
has since 1988 made significant progress towards its goal of a successful
commercial future. Full commercial viability will require significant
growth and perhaps some financial reconstruction (see paragraph 1.23).
AEA's individual businesses are mostly still quite small and their profitable
expansion is by no means assured, but we were impressed by the expertise,
enthusiasm and dedication of their staff.
Full text
Contents
|
Chapters
|
|
| Chapter
1 |
Assessment |
| Chapter
2 |
Structure and organisation |
| Chapter
3 |
Planning |
| Chapter
4 |
Financial framework and control |
| Chapter
5 |
Management and financial information systems |
| Chapter
6 |
Use of physical assets |
| Chapter
7 |
Industrial relations, pay and employment policies |
| Chapter
8 |
Efficient use of manpower |
| Chapter
9 |
Restructuring programme |
| Chapter
10 |
Corporate research and development |
| Chapter
11 |
Investment |
| Chapter
12 |
Project management |
| Chapter
13 |
Marketing |
| Chapter
14 |
Pricing |
| Chapter
15 |
Safety |
| Chapter
16 |
Quality of goods and services |
| Chapter
17 |
Summary of recommendations |
| |
List of signatories |
| Glossary |
|
Appendices
|
|
| (The numbering of the appendices indicates
the chapters to which they relate) |
| 1.1 |
The reference and background |
| 1.2 |
Third parties who submitted views |
| 1.3 |
Text of a letter from the Secretary of State to the AEA
Chairman, 21 February 1991 |
| 2.1 |
Corporate Headquarters, 1 April 1991 |
| 2.2 |
The structure of the top committees in AEA |
| 2.3 |
The AEA businesses |
| 2.4 |
Corporate DRAWMOPS Board of Management terms of reference |
| 3.1 |
Board members' bonus scheme for 1991/92 |
| 3.2 |
AEA's mission and values statement |
| 5.1 |
AEA IT facilities by site |
| 5.2 |
AEA current accounting systems architecture |
| 5.3 |
Northern sites current accounting systems architecture |
| 5.4 |
Regular management reports |
| 5.5 |
CFACS system as installed in each AEA business |
| 5.6 |
Linkages between each AEA business and CHQ from April
1992 |
| 7.1 |
Off-the-job training statistics, 1987 to 1991 |
| 7.2 |
Current organisation of personnel service |
| 7.3 |
Proposed corporate personnel and training service from
April 1992 |
| 9.1 |
Definitions of circumstances and costs qualifying for
repayment from the fast reactor/fusion restructuring grants
(extract from a Programme Letter) |
| 11.1 |
Case studies of investment projects |
| 11.2 |
AEA capital and revenue schemes completed since 1 April
1990 or currently in progress |
| 11.3 |
AEA revenue and capital schemes approved between April
1990 and September 1991 |
| 12.1 |
Duties of a proposal manager |
| 12.2 |
Duties of a project manager |
| 12.3 |
Earned value |
| 12.4 |
Example of an earned value bulk activity chart |
| 14.1 |
DEn Programme Letters |
| 16.1 |
MMC survey of AEA customers |