Northern Ireland Electricity Plc: A report on a reference
under Article 15 of the Electricity (Northern Ireland) Order 1992
Summary of report (html format)
Full text (pdf format)
Adobe Acrobat Reader can be downloaded from http://www.adobe.com
Summary
On 18 September 1996 the Director General of Electricity Supply for Northern
Ireland (the DG) made a reference to us under the Electric-ity (Northern
Ireland) Order 1992 (the Electricity Order) concern-ing two sets of price
controls in the licence of Northern Ireland Electricity plc (NIE). The
terms of reference are set out in Appendix 1.1.
The structure of the electricity supply industry in Northern Ireland
is different from that in Great Britain. The generating sector is almost
all in the hands of three private sector companies to which the power
stations were sold in 1992. NIE, which was privatized in June 1993, has
a statutory monopoly of transmission and distribution (T&D) in Northern
Ireland and is the Public Electricity Supplier (PES) for the province.
It also has a Power Procurement Business (PPB) which has a statutory monopoly
in both the purchasing of wholesale electricity from generators and its
sale to suppliers. NIE's Supply Business is in principle open to competition
and three companies have been granted second-tier supply licences but
their share of the market to date is well under 1 per cent.
During 1995 and 1996 the DG carried out a review of the price controls
on NIE's three main regulated businesses-the PPB, the T&D Business
and the Supply Business-and published proposals for revised controls to
apply from 1 April 1997. NIE accepted the pro-posals for the PPB but rejected
those for T&D and Supply. Consequently the DG referred these matters
to us. Our terms of reference require us to report on whether the continuation
without modification of the provisions in Schedule 4 to NIE's licence,
which restrict NIE's T&D charges, and the provisions in Schedule 6
which restrict its Supply charges, in either case operates or may be expected
to operate against the public interest; and if so, whether the effects
adverse to the public interest could be remedied or prevented by modifications
to the licence.
In considering the appropriate level of price controls on the T&D
Business we have adopted the following:
(a) a cost of capital of 7 per cent;
(b) a value of £370 million for the asset base of the business
at privatization, at 1993/94 prices; after allowing for new investment
since then, for depreciation and for inflation, that led us to a value
of £475 million at 1996/97 prices for the asset base as at the begin-ning
of the forthcoming regulatory period;
(c) a level of £310 million (at 1996/97 prices), after deducting
customer contributions, for capital expenditure over the next five years;
and
(d) an amount of £328 million (at 1996/97 prices) for operating
expen-diture over that period.
For the purpose of our calculations we have also made a downward adjustment
because of the extent and nature of the capital underspend in the period
since privatization.
On the basis of these assessments we consider that the price control
for the next five years should be set to give NIE total revenues from
its T&D Business with a net present value (NPV) of £575 million
at 1996/97 prices. We also propose that the term in the price formula
concerning electricity losses, which is intended to give NIE an incentive
to reduce the rate of losses, should be reduced from 10.5 to 10 per cent
in line with the DG's proposals.
Continuation without modification of the present price controls would
lead to revenues far higher than the amount referred to in paragraph 1.5.
We therefore concluded that continu-ation of the existing provisions of
Schedule 4 may be expected to operate against the public interest and
that the adverse effects which we identified could be prevented by modifications
to those provisions. Specifically, we propose that revenues allowed by
the price control formula should be reduced by 25 per cent in 1997/98,
compared with the level allowed in 1996/97, and should fall by 2 per cent
in real terms in each of the four subsequent years of the period.
The Supply Business requires relatively little capital expenditure and
the key element affecting its need for finance is operating expenditure.
In reviewing the price controls on the business we adopted:
(a) an amount of £90 million (at 1996/97 prices) for operating
expenditure over the next five years;
(b) an amount of £0.6 million a year for energy efficiency activities,
as proposed by the DG; and
(c) a return of 0.5 per cent on total turnover as a suitable level of
profit. Turnover is very high in relation to the costs of the Supply Business
because it includes the pass-through of electricity and T&D costs.
A rate of 0.5 per cent on turnover would give the business about £11.5
million in profit, at 1996/97 prices, over the five years.
On this basis we consider that the price control for the next five years
should be set to give NIE total revenues for its Supply Business of £105
million at 1996/97 prices.
Continuation without modificat-ion of the present price controls would
lead to revenues well above this level. We therefore concluded that the
continuation of the existing provisions of Schedule 6 may be expected
to operate against the public interest and that the adverse effects which
we identified could be prevented by modifications to those provisions.
We propose modifications which would entail a reduction of 42 per cent
in the revenues allowed under the formula in 1997/98, compared with 1996/97,
and a real reduction of 2 per cent a year in the following four years.
We estimate that the effect of our proposals will be to reduce domestic
electricity prices in Northern Ireland by about 14 per cent in real terms
between 1996/97 and 1997/98. The first-year reduction for large industrial
customers will be smaller, about 5 per cent, because generation costs
account for a much higher proportion of the final price to them than for
domestic customers. These estimates do not take account of changes in
the generation component of electricity prices, or the deployment of the
sum which the Government is providing to reduce prices in Northern Ireland,
neither of which is affected by our inquiry. The reductions are a little
lower than those which would have resulted from implementation of the
DG's proposals, but greater than those implied by NIE's counter-proposals.
The amounts which we have adopted for capital and operating expenditure
will provide a basis for NIE to achieve, in a number of respects, a better
quality of service than would have been likely under the DG's proposals.
Full text
Contents
|
Part I
|
Summary and Conclusions
|
| Chapter 1 |
Summary |
| Chapter 2 |
Conclusions |
Part II
|
Background and evidence
|
| Chapter 3 |
Northern Ireland and its electricity supply industry |
| Chapter 4 |
The regulatory background |
| Chapter 5 |
History, activities and financial performance of NIE |
| Chapter 6 |
Quality of service |
| Chapter 7 |
The capital investment programme of NIE |
| Chapter 8 |
The operational efficiency of NIE |
| Chapter 9 |
Cost of capital and financial projections |
| Chapter 10 |
Views of NIE |
| Chapter 11 |
Views of the DG |
| Chapter 12 |
Views of third parties |
| |
List of signatories |
Appendices
|
|
| (The numbering of the appendices indicates
the chapters to which they relate) |
| 1.1 |
The reference and background |
| 2.1 |
Schedule 4 to NIE's licence |
| 2.2 |
Schedule 6 to NIE's licence |
| 2.3 |
Articles 4 and 6 of the Electricity (Northern Ireland)
Order 1992 |
| 2.4 |
The MMC's calculations of possible valuations for NIE
at flotation, based on its prospectus |
| 2.5 |
Effect of MMC proposal concerning depreciation |
| 2.6 |
Derivation of opening and closing values of the RAB for
the T&D Business |
| 2.7 |
Calculation of NPV effect of adjustment for underspend |
| 2.8 |
The MMC's assessment of an efficient level of operating
expenditure for NIE |
| 3.1 |
Generating plant capacity, contract expiry dates and
earliest cancellation dates |
| 3.2 |
PESs' views on the supply market in Northern Ireland |
| 3.3 |
NIE's tariffs |
| 3.4 |
Prices to domestic customers, 1990/91 to 1996/97 |
| 3.5 |
Privatization and regulation of the electricity supply
industry in the UK |
| 3.6 |
Average domestic bill by fuel component in 1996/ 97 |
| 5.1 |
NIE Board members and Board Committees |
| 5.2 |
Principal subsidiary undertakings of NIE at 31 March
1996 |
| 5.3 |
Extracts from NIE's prospectus at June 1993 |
| 6.1 |
New standards of performance for NIE proposed by OFREG |
| 6.2 |
Main findings of OFREG's market research survey |
| 7.1 |
NIE: details of capital expenditure underspend for period
1992/93 to 1996/97 |
| 7.2 |
NIE's internal guidance on the categorization of network
expenditure between capital and revenue |
| 8.1 |
Organization and organizational changes |
| 8.2 |
Manpower costs, planning and productivity |
| 8.3 |
The views of NIE and the DG on comparators |
| 8.4 |
Comparative studies of NIE's operating efficiency |
| 9.1 |
The CAPM and the DGM |
|
9.2
|
[Details
omitted. See note page iv.] |
| 9.3 |
Comparison of debt premia in 1996 |
| 9.4 |
Analysts' estimates of NIE's profits and NIE's actual
profits |
| 9.5 |
Information on NIE from the prospectus and from brokers'
reports in 1992 and 1993 |
| 9.6 |
A note by NIE on its estimate of its initial price control
value |
| 9.7 |
HCA fixed asset summary from 31 March 1992 to 31 March
1996 |
| 9.8 |
CCA fixed asset summary from 31 March 1992 to 31 March
1996 |
| 12.1 |
Members of the Action Group on Northern Ireland Energy
Issues |
| Glossary |
|
| Index |
|
Back to the top
|